CB240 formasyna çykmak
Düşündirişler
Platform width: 2.4m
Roll-back system: 70 cm with carriage and rack system
Finishing platform: for removing the climbing cone, polishing concrete surface etc.
Anchor system: should be pre-fixed into the formwork and left in the concrete after pouring.
Formwork: can be moved horizontally, vertically and tilted to meet site requirement.
Main platform: provide workers a safe working platform
Finishing platform: there is an access to the main platform by using a safety ladder.
Üstünlikleri
- Constrhli Gurluşyk diwar formalaryna laýyk gelýär.
- Garaşanlardan we forma panellerinden düzülen toplumlar, kran göteriji bilen indiki guýulýan ädimine geçirilýär.
- Göni, ýapgyt we tegelek diwarlary goşmak bilen islendik gurluşlara uýgunlaşdyrylýar.
- Dürli derejelerde iş platformalaryny gurmak mümkin. Howpsuzlyk merdiwanlary bilen üpjün edilen platformalara giriş.
- Brahli ýaýyň içinde tutawaçlary, gysgyçlary we beýleki esbaplary düzeltmek üçin ähli birikdirijiler bar.
- Dyrmaşýan ýaýlar, wagondan we tekerden emele gelen ulgamy öz içine alýan ulgam panellerini yzyna gaýtarmaga mümkinçilik berýär.
- Formwork’s vertical adjusting and plumbing is completedwithleveling screw jacks and push-pull props.
- Braketler labyr konus ulgamy bilen diwara dakylýar.
Dyrmaşmak tertibi
The first pouring is to be completed by using the proper wall elements and has to be exactly sazlaýjy struts bilen deňleşdirildi. |
2-nji ädim The completely pre-assembled climbing scaffold units consisting of climbing brackets with plank bottom and bracing have to be attached to the bracket anchoring and secured. Then the formwork and the move-off carriage together with the aligning beam has to be positioned on the brackets and fixed. |
3-nji ädim After shifting the climbing scaffold unit to the next pouring position the finishing platform is to be mounted to the brackets to complete the climbing system. |
4-nji ädim Release and remove bolts that fixing the positioning anchor point. Galstugy gowşadyň we aýryň Loosen the wedges of the carriage unit. |
5-nji ädim Retract the carriage and lock it with wedge. Upperokarky dyrmaşma konuslaryny guruň Windel goraýjy enjamy bar bolsa gowşadyň Aşaky dyrmaşma konusyny aýryň
|
6-njy ädim Adjust the carriage into the common center of gravity and lock it again. Kran slingini dik aýlaw bilen dakyň Garaşygyň gorag boltlaryny aýryň Lift the climbing bracket by crane and attach it to the next prepared climbing cone. Howpsuzlyk boltlaryny täzeden salyň we gulplaň. Zerur bolsa, ýel ýükleýän enjamy guruň. |
7-nji ädim Move the carriage back and lock it by wedge. Formany arassalaň. Berkidiji panelleri guruň. |
8-nji ädim Move the formwork forward until lower end rests against top of the finished section of the wall Çekiş ýaýynyň kömegi bilen forma işini dikligine sazlaň. Diwaryň ýasalmagy üçin galstuklary düzediň |